Data Center Colocation Pricing

Colocation is priced by power, not space. The key measures are how many kW you can use reliably each month and how much heat the facility can remove.

What determines the price

The monthly price for the same rack can vary by more than twofold between facilities. Three factors explain the difference.

01

Power capacity and density

Pricing is based on kW per month. High-density racks above 40kW require different power distribution and cooling designs, so their unit cost is higher than a standard 5kW rack.

  • Priced per kW per month
  • Rack densities from 5kW to 40kW+
  • Includes PDU and downstream power distribution
02

Cooling method

Air cooling, direct-to-chip liquid cooling (DTC), immersion cooling, and hybrid systems have different construction costs and PUE performance. Those differences affect both monthly charges and long-term electricity costs.

  • Air cooling, including hot-aisle and cold-aisle containment
  • Direct-to-chip liquid cooling (DTC)
  • Immersion cooling
  • Hybrid cooling
03

Facility tier and certifications

The Tier rating determines redundancy and availability commitments. Certifications determine whether the facility may host data for specific industries.

  • Tier I / II / III / IV / Beyond Tier IV
  • ISO 27001 and other certifications
  • Continent, country, and city

Fields to compare when choosing a facility

The current data center search includes these filters. Use them to narrow the shortlist before requesting a quote.

FilterAvailable rangeWhy it affects price
LocationContinent · Country · CityElectricity, land, and labor costs, as well as data residency rules
Tier ratingI · II · III · IV · Beyond Tier IVThe redundancy level determines how much electrical and mechanical equipment must be duplicated
Cooling typeAir · Liquid DTC · Immersion · HybridThe cooling design determines supported rack density and PUE
CertificationsISO 27001 and othersCompliance requirements narrow the available facilities, reducing supply and increasing price
Power capacity0 to 100 MWLarger sites have lower unit costs but longer delivery schedules
PricePer kW per monthThe final basis for comparison

What the monthly fee includes

Usually included

Up to the kW capacity stated in the contract.

  • Rack space and hot-aisle or cold-aisle containment
  • Downstream power distribution and rack PDUs
  • Cooling capacity from air-conditioning and water systems
  • Environmental monitoring and access control
  • Clean-agent fire suppression
  • Basic network connection

Priced separately

These items are billed by actual usage or service call.

  • Power use above the contracted capacity
  • Inter-site private lines and bandwidth
  • Remote operations and data center access on the client's behalf (remote hands)
  • Client-specific network segments or firewalls
  • Hardware transport and rack installation labor

FAQ

Why is pricing based on kW instead of the number of racks?
AI rack power varies widely. A 5kW rack of conventional equipment and a 40kW rack of GPU servers occupy about the same space, but the latter uses eight times as much power and cooling. Pricing by rack would not reflect the resources consumed.
Is there a minimum contracted capacity?
Yes, and it varies by facility. High-density zones usually start at a full rack, while lower-density zones may accept a half rack.
Can deployments span multiple countries?
Yes. Current operational and planned sites cover Taiwan, Japan, Thailand, the Czech Republic, Texas in the United States, Singapore, Malaysia, and Indonesia.
Who handles failures in client-owned hardware?
The equipment manufacturer handles the warranty and RMA. We diagnose issues on site, replace components, and coordinate repairs, with response times defined in the 24×7 operations contract.